KL-90 BY KIKO’S LAB
GERALD 65
- Keyboard orders have begun fulfillment
- The wrist rests are still with the manufacturer, as per Aidan (Designer)
Ikki Aurora R1
ORDERS FULFILLED
RADIANCE TKL
- Orders submitted
- Items are in production
- Waiting for additional updates from the manufacturer
- Radiance tkl is done in production, awaiting shipping
SUN 68
NK65 Milkshake R1
GHS.RAR
MR SUIT R1
MR SUIT R2
COARSE 60 BY KEEBS FOR ALL
- Orders submitted
MR. SUIT R3
JELLY EPOCH 75%
SPRING KEYBOARD BY OWLABS
- Orders submitted
- Tally final count is also submitted and reviewed by team.
- Latest update as of today: 04/18/22 Items are for shipping now to Zion China warehouse.
- Latest update: 04/25/22 Preparing for shipment both international and philippines
- 100% Spring boards arrived to PH office
- 05/13/22 – Some springs already left the office for international, ongoing fulfillment
- 05/13/22 – Spring order for PH already left office, ETA 3-3.5 weeks
- 05/13/22 – Missing 10 springs for PH left office, ETA 4-4.5 weeks
- 05/24/22 – Majority of the springs has arrived at PH Zion office, will start shipping tomorrow
- 05/24/22 – Missing 10 springs orders are still in transit, waiting time is 1 week or less
- 05/24/22 – International fulfillment still ongoing
Air shipping: Phlippines clients
- Arrived at the office of Zion Studios (PH Office)
Shipping starts today, Same day / J&T Depending on the client’s location
06/01/22 Some spring items are still with us, waiting for some missing items, but coordinated already with owlabs. We apologize for the delay.
Batch of spring boards that were late in transit is expected to arrive this week at PH Office.
06/16/2022 – The remaining 10 springs are still in SEA. A bit of a bad news as bad weather is forecasted and the springs are on those ship that is affected by bad weather. We will have more updates soon.
07/12/2022
Fulfilllment progress at 95% completion.
NK65 MILKSHAKE R2
ORDERS FULFILLED
IKKI AURORA PEACHES & CREAM
- Orders fulfilled
- Missing orders are taken care of by Zion Team.
IKKI AURORA WINTERBREATH
ORDERS FULFILLED
IKKI AURORA ALU TOP CASE (SNOW)
- Orders submitted
- Waiting for additional updates from the manufacturer.
- Ikki-68 aurora winterbreath, ikki-68 round 2 will be delivered around second to third week of may to vendors. Production for both items is almost done
-
05/24/22
The items has already arrived in our office last friday. For those who internationally ordered from us, please kindly wait as fulfillment is ongoing already.
Orders for PH has left the office last friday, ETA 4 weeks
ZOOM 65 [PRE-ORDER 1] OLIVIA DARK
Orders fulfilled
Mammoth 75/20 GB
Our manufacturer finished part CNC work, and continue working for other CNC cases in April. We are following our schedule for in-time delivery.
05/02/2022 We finished 80% Mammoth75 and 100% Mammoth20 CNC work. We are following our schedule for in-time delivery.
07/12/2022
The CNC for the Mammoth keyboard kit is done. Our manufacturer is QC-inspecting Mammoth keyboard kits, assembling and packaging the QC-inspected Mammoth keyboard kits.
ZOOM 65 [PRE-ORDER 2] OLIVIA DARK
- Orders submitted
- For shipping to vendors
- 04/07/2022 – For shipping to Philippines by sea freight, ETA 3-4 weeks, assuming there are no upcoming lockdowns and hold of customs parcels on China/PH
ORDERS FULFILLED
FREEBIRD TKL
- Orders submitted
- There will be a delay in FBTKL and Numpads production because KFA has received the funds from few vendors late. ETA: July-Aug 2022.
- 07/12/2022 Arriving to Zion CN soon
FREEBIRD NUMPAD
- Orders submitted
- There will be a delay in FBTKL and Numpads production because KFA has received the funds from few vendors late. ETA: July-Aug 2022.
IKKI AURORA DREAMSCAPE
- Orders fulfilled
FREEBIRD60
- Orders fulfilled
FREEBIRD60 (CASE ONLY)
- Orders fulfilled
HAVEN 60% KEYBOARD
- Orders submitted
- In production
- Waiting for additional updates from the manufacturer.
FLAME 60
- Orders submitted
- Waiting for additional updates from the manufacturer
- ETA shipping to vendors: May 2022
- 04/25/2022 Manufacturer encounter problems with lockdown. The CNC production is being limited in progress hours due to the constant lockdown being imposed in china.
QWERTYKEYS 65%
- GB ended
- Orders have been submitted to manufacturer.
- Waiting for additional updates
- Target schedule to vendors: June 2022
- 06/01/22 Items has been received at the Zion China office. Items are preparing for shipment. Team is doing a count on the items first before we ship the boards. A different tab update will be given when the board is out of CN office.
07/12/2022
Fulfillment Progress: 75% Completion
RADIANCE TKL
- GB ended
- Orders have been submitted to manufacturer.
- Waiting for additional updates
- 05/17/22 Radiance TKL Has finished production and is for shipping to Zion china